Feasibility Studies

Site identification, surveys, data analysis, environmental impact assessments, designing of civil and electromechanical equipment and development of detailed feasibility reports are main component of feasibility studies.

So far detailed feasibilities of 19 Mini Micro Hydropower Projects have been completed.

The salient features of the projects are as under:-

S # Name of Project Capacity (kW) Annual Electricity Production (MWH) Cost of Electricity

PKR (Millions)

1 Banda Gisuch 15 88 0.53
2 Chinarkot 50 292 1.75
3 Jaba Sum 75 438 2.63
4 Seri Manoor 75 438 2.63
5 Dum Duma 100 657 3.94
6 Khanian 100 657 3.94
7 Battal 150 986 5.91
8 Sum 150 986 5.91
9 Kery 200 1314 7.88
10 Kot Klai Dhanan 200 1314 7.88
11 Batakundi 250 1643 9.86
12 Upper Naran 250 1643 9.86
13 Kotkay 300 1971 11.83
14 Mahandri 300 1971 11.83
15 Behari 400 2628 15.77
16 Devli 400 2628 15.77
17 Bela Manoor 500 3285 19.71
18 Makhan Gali 500 3285 19.71
19 Naran 500 3285 19.71
Total 4,515 29,507 177.04